On 6/12/18 1:20 AM, Christopher wrote:

Again, I am stating that a timeline with no recognition of what work
needs to be done is silly. Yes, you can draw a line in the sand for when
you want work to be done, but that's ineffective in making an actionable
feature complete date.

If you want the date to be meaningful, you need to understand what work
actually _has_ to be done and structure the date around that. Does this
make sense?

I thought you were saying that there were too many open issues on Jira
to glean any information on outstanding work from it. I was trying to
give a suggestion about how to move past that.